"I do not remember having had such an enjoyable experience as that which we have enjoyed under your careful guidance."

The Royal Naval Benevolent Trust
Project Details

Kent Science Park - Technology Units


kent-science-park-tech-1-tb.gif We were delighted to be chosen for the "first entirely new buildings" at Kent Science Park.

The new 22,600 ft2 Technology Units initially £1.8m, were completed within the 30 week programme.
Additional tenants 'fit-out' works
extended the final account



This 'design and construct' contract included challenges with:

This project followed several major refurbishment projects for Kent
Science Park.